Pengerukan Kali Grogol Segmen Susilo Capai 99 Persen

Grogol River Dredging on Susilo Segment Touches 99 Percent

The West Jakarta Water Resources (SDA) Sub-agency continues to accelerate dredging work on the Segment II Susilo of Grogol River, Jalan Latumenten, Grogol, Grogol Petamburan.

It is carried out to increase the river's capacity

The progress of river dredging work which began on February 20, 2020, has now reached 99 percent.

West Jakarta SDA Sub-agency Head, Purwanti stated, her side used heavy equipment to dredge mud on Grogol River with a depth of 2 meters.

Jakarta Doesn't Appeal to Administrative Court Decision Regarding Flood Handling

"It is carried out to increase the river's capacity," she mentioned, Friday (3/11).

As a result, her side could transport mud to 10 dump trucks a day. Later on, dredging on the river would be continued to the Borobudur Pump area.

"Hopefully, the Grogol area will be free from inundation after the dredging," she conveyed.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye887 personAldi Geri Lumban Tobing
  2. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye598 personAldi Geri Lumban Tobing
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye574 personDessy Suciati
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye562 personFakhrizal Fakhri
  5. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye422 personNurito